3850 had its last day in service on 30th September 2015 before beginning a heavy overhaul. The loco has run for 1202 days in traffic and covered 81,988 miles since entering service in March 2006 – all but 46 days of the service were on the West Somerset Railway, the other days being a visit to the Great Central Railway in 2011, a brief visit to the Gloucestershire Warwickshire (GWSR) for a Gala in 2014 and a final few days back there in September to allow the volunteers some running time – plus the opportunity for some of our shareholders to have a short drive! The picture shows 3850 at Minehead in 2011 shortly after its repaint into black – photo by John Sparks
Pictured here is the “final fire” before withdrawal – appropriately this was lit and tended by the Vice Chairman of the Company (Mike Solloway) – Mike was on the footplate for the first run back in 2006 and to make the day even more special he passed out as a qualified Fireman on the GWSR during his shift.
The work of stripping her down has started in earnest and the parts are coming off thick and fast – superheater elements came out on 8th November and the last of the cladding was also removed that day – along with the cab roof.
All boiler tubes have been removed and the boiler itself was lifted from the frames in early May. Unfortunately we have found a fairly serious crack in our cylinder block and think it most likely that a replacement is needed – we have already done some of the preparatory work to source a new casting.
A close up of the problem!
Preparation of the boiler for non-destructive testing and scoping of the works required is well underway with needle gunning at every opportunity – both inside and out
A view up the barrel – since this photo was taken the smoke box has been removed (though it was a struggle!)
It became clear that new cylinders were required!!!
3850’s cylinders and frames stretchers split from the mainframe to facilitate the fitting of the new cylinders
Blocks and accommodation bogies ready to take the weight.
Frame stretcher moving away from the frames
Hydraulic power keeps it moving
JOB DONE and a happy crew!

Now we need to get the new cylinders fitted and put it all back together!
One of the pair of new cylinders when just cast.
It does look a bit rough but will no doubt look better after the sand blasting – then will come the machining.
We now jump forward several years - we were hit by Covid 19 which set us back by months when volunteering could not be undertaken. The boiler was fully overhauled by Riley & Son in Lancashire and came back for installation in the fully overhauled frames.

The came the cladding and painting

Getting closer
3850 Entered service on the GWSR in September 2024








